
"We have already built the most powerful AI training clusters in the world," Musk told SpaceX employees at a meeting. "What we expect to do by the end of next year is about 10 times more than what we have done thus far. […] So, we are aiming to get to 10 GW [of compute] by the end of next year. […] If the value per watt is probably going to be $30 to $50, which means if we bring 10 GW of AI compute online by the end of next year, it will be $300 to $500 billion a year in revenue. Big numbers."
At present, SpaceX's xAI data centers in Memphis and Southaven have a rated power draw of 1.4 GW. The company plans to increase the electrical capacity of its data centers to 10 GW by the end of 2027, or by around sevenfold in roughly 1.5 years. It should be noted that AI infrastructure with a 'nameplate power draw' of 1.4 GW by far does not offer compute capacity of 1.4 GW.
A large AI data center with a power usage effectiveness (PUE) of roughly 1.2 would have around 1.17 GW available to IT equipment (i.e., 230 MW is used by cooling, pumps, fans, humidification/dehumidification, lighting, power distribution losses, UPS losses, and other facility systems). Not all of that 1.17 GW goes to AI accelerators: CPUs, memory, networking, and storage consume a meaningful share. If perhaps 70% – 80% of IT power ultimately corresponds to accelerators, we might be looking at roughly 0.8 GW – 0.95 GW of accelerator power in the case of a 1.4 GW data center.
Compute capacity is not measured in Watts; it is measured in floating-point operations per second (FLOPS). Keeping in mind that currently xAI uses a mix of Hopper- and Blackwell-based accelerators, it is hard to determine how much compute xAI has today. Since xAI seems to be betting primarily at Nvidia's Vera Rubin systems from now on , we can make a more or less educated guess about the company's Rubin-based compute capability the company will have by the end of 2027.
SpaceX unveils 11-million-square-foot Gigasat factory, a new manufacturing facility for space-based data centers
Elon Musk's first-gen orbital data center craft spans wider than a Boeing 747 and runs an interchangeable chip payload
Meta expands colossal Hyperion AI supercluster plans to 5GW, pushes Louisiana investment past $50 billion as AI race accelerates
Assuming that all of the new 8.6 GW nameplate power draw will be based on Nvidia's NVL72 VR200 rack-scale systems and the PUE of around 1.2, the IT power budget of the new capacity will be 6.88 GW. Actual Rubin AI accelerators will get between 4.816 GW and 5.504 GW of power depending on how much of the IT power will correspond to these GPUs. Each Rubin GPU is expected to consume 2.3 kW of power in Max-P configuration. As a result, xAI's clusters will house between 2.094 million and 2.393 million Rubin GPUs in Max-P mode, or 29,083 and 33,236 NVL72 VR200 systems.
The performance of the NVL72 VR200 system is well known , so depending on the number of these machines that xAI will deploy by the end of 2027, we are looking at rather formidable numbers. NVFP4 inference performance of the cluster will be between 105 and 120 ExaFLOPS; NVFP4 training performance will range from 73 to 84 ExaFLOPS; FP6/FP8 training capability is projected between 37 and 42 EFLOPS, whereas native FP64 compute will total 70 – 80 EFLOPS. Of course, we are dealing with very rough numbers here as some systems may not work in Max-P configuration.
Get Tom's Hardware's best news and in-depth reviews, straight to your inbox.
Key considerations
- Investor positioning can change fast
- Volatility remains possible near catalysts
- Macro rates and liquidity can dominate flows
Reference reading
- https://www.tomshardware.com/tech-industry/artificial-intelligence/SPONSORED_LINK_URL
- https://www.tomshardware.com/tech-industry/artificial-intelligence/elon-musk-says-xai-will-increase-data-center-capacity-7x-by-2027-targeting-10-gigawatts-of-compute-up-to-usd500-billion-in-revenue-by-the-end-of-next-year#main
- https://www.tomshardware.com/membership
- NVIDIA Harnesses Vera CPU to Speed Up Design of Next-Generation CPUs and GPUs
- Alabama residents left powerless to stop massive Bitcoin mining data center despite county and town moratoriums — hole in state zoning laws lets facility throug
- Near-packaged optics (NPO) gains ground as the industry hedges against CPO's growing pains — analysts say volume for NPO silicon photonics products will extend
- Save $106 on this 4TB Team Group SSD with Gen 4 speeds, now 10.2 cents per GB — Newegg coupon deal makes this T-Force G50 one of the cheapest PCIe 4.0 drives on
- Prusa Research XL, Core One, and Core One L all to receive second-generation upgrades — all new orders get updated model for 'free'
Informational only. No financial advice. Do your own research.